Revere Dock Wall

Ericksons worked to remediate a failing dock wall in Detroit and looked to Nucor Skyline to help. Nucor Skyline supplied HP 14x73 H-piles as foundational support. A combination-wall at the site was built using Nucor Skyline’s NZ 19 sheet piles and 54” OD pipe with E22 connectors.

Location: Detroit, MI

Partners: Owner: Ericksons; Engineer: G2 Consulting Group; Driving Contractor: Great Lakes Dock and Materials, LLC

Products: HP 14x73 (782 tons), NZ 19 sheet piles (315 tons), 54” x 0.625” pipe (1,660 tons) and E22 connectors (50 tons)