Van Wyck Expressway

Tully Construction Co., Inc. worked with STV on the Design-Build-Operate-Maintain (DBOM) contract. Tri-State Civil Construction LLC was contracted as the drilling contractor and used Nucor Skyline casings and threaded bars on the project. Seventy-eight micropiles were installed at location one and 58 micropiles will be installed at location two.

Loaction: Queens, NY

Partners: Owner: New York State Department of Transportation;
General Contractor: Tully Construction Co., Inc.; Engineer/Designer: STV; Drilling Contractor: Tri-State Civil Construction LLC

Products: 10¾” x .500” Prime domestic casing; #24 domestic Gr. 80 threaded bar - micropile capacity 60 to 120 tons