Loup Power District

Midwest Infrastructure, Inc. used Nucor Skyline PZ 27 and SKS 14 sheet piles to install a 287 foot long steel sheet pile wall that helped restore the integrity of the Loup Canal and the associated facilities. Midwest also constructed a 45 ft. long sheet pile cut-off wall, with the associated wall support and channel reinforcements.

Location: Lincoln, NE

Partners: Owner: Loup Power District; General Contractor: Midwest Infrastructure Inc.; Engineer: JEO Consulting Group, Inc.

Products: PZ 27 and SKS 14 sheet piles – 140 tons 